WINTHROP FIREHOUSE BUILDING COMMITTEE MEETING 
August 13, 2025, Harvey Hearing Room 
CALL TO ORDER – 5:00pm 
ROLL CALL 
Present: Scott Wiley (SW), Stephen Calandra (SC), Jim Letterie (JL), Karin Chavis (KC), Jack Dempsy (JD), Hannah 
Belcher (HB), Tony Marino (TM), Joe Hanlon (JH) 
Absent: Jill Dorr, Kim Dimes, Paul Flanagan, Shannon Poulos 
Other Attendees: Dan Pallotta, P3 (DP), Larry Trim (KBA), Seung Hwan Lee (KBA) 
PLEDGE OF ALLEGIANCE 
MINUTES 
Approval of Minutes, July 29th, 2025 as circulated 
motion by JD, 2 nd by SC; Unanimously approved 
OPM UPDATE 
• Dan away 8/24-9/8, Mark Champagne will be backup 
• Test beds have been established to check for mastic below grade 
• 50/50 chance that it is found; if none, much easier/less costly 
• All utilities can be capped 
• Emergency response for gym & rink tied into old middle school 
• Will need to relocate that system – already started running fiberoptics for fire response – 
adding remote dialer 
• Larry/Seung Hwan have looked at archives and visited site 
• Visually checked foundations 
• Can find all drawings of site EXCEPT structural drawings 
• Water/electrical/etc. will be easy to cut and cap 
• Can cut utility lines to make old middle school building ‘free standing’ 
• Can visually see old high school foundation 
• Unclear if all debris was removed when that building was taken down 
• May need to enclose wall of Auditorium 
• Could cut/cap at top of auditorium (near old drama room) 
• Dan will provide drawings to Tony for DPW to dig appropriate test beds 
DISCUSSION 
JL: Need to talk to abutters before test beds are dug 
DP: Yes, abutters will be informed; just need to dig down deep enough to check for mastic, but the building’s 
footing is not that deep

JL: Cellucci Tree needs to be carefully relocated/remain safe during construction. Also need to understand parking 
availability during demo 
DP: Demolition company determines staging/order of demo project, so no clear answers on parking etc. yet 
• Demo requests will be on register right before labor day, anticipate having all relevant drawings by 
the Wednesday after 
o Anticipate 4-5 bids 
o Still waiting on utility survey – should have by end of month 
Next Meeting: Monday, Sept. 29 th , 5pm – will start discussion of design 
DP: will use paper bidding process (IFB) to help keep cost down 
- All site visits have to be POSTED, but do not need to be open to the public 
ADJOURNMENT 
motion by JL ,2 nd by TM; Passed unanimously 
Adjourned 5:37pm